Location

Reston, VA

Contact

Not listed contact Scott Palmer for more information

Performance

PCG

Scope

Interior finish out and roof

Maximus Data Center

Sometimes PGC is called on to step in when another contractor cannot complete a job. That means working seamlessly with existing subcontractors to finish the project on time and on budget. This project involved the completion of construction on a data center interior and roof. PGC’s work included the following:

  1. Raised flooring and removal of all water piping
  2. Installed FM 200 sprinkler system and pre-action sprinkler system
  3. Completed smoke-sealed rooms
  4. Installed large Liebert A/C units
  5. Completed roofing work, including steel fabricated cat walks, parapets and lighting